| Borough of Havant - Home | Whats New | Site Map | Search | Help | Complaints | Terms and Conditions | Feedback | Web Accessibility | Skip Nav |
Skip Navigation

Further information on Beach Nourishment and Navigational Dredge projects

 

Beach Nourishment 2008 - Phase 1

 

After completing two stages of urgent interim works in 2007, Havant Borough Council successfully gained approval from the Environment Agency for the full Beach Nourishment scheme to raise the beach to the recommended 1 in 200 year standard of protection with design life, once was funding is available.  The first phase of the works was successfully carried out between September and October 2008 which involved placing 25,000m³  of material on the Eastoke frontage.

 

The Council appointed Westminster Dredging Ltd who undertook the works using the dredging vessel "Sospan Dau" which was previously used for similar works at Eastoke in 2007, 2002 and 1997. The vessel was a trailing suction hopper dredger, approximately 70 metres long and capable of holding 900 cubic metres of sand and gravel.  The dredger had a shallow draft and a jet pump ashore facility, which enables the vessel to come very close inshore and "rainbow" the material directly into its preferred location.

 

The dredger rainbowing beach nourishment material

 

 

Urgent Interim Works June 2007

 

Havant Borough Council applied for funding for a full Beach Nourishment scheme to place 150,000m3 of material on the southern frontage of the Eastoke Peninsula. 

 

Unfortunately, the Department for Environment, Food & Rural Affairs (DEFRA) announced at the end of 2006 that there was no funding to carry out the full scheme to raise the beach to the required 1 in 200 year standard of protection.

 

However, the council managed to obtain funding from DEFRA and the Environment Agency for interim urgent works for a small portion of the material to raise the beach level and the standard of protection in the mean time.  This urgent interim work was carried out in two stages. The first stage was completed in June 2007 when approximately 60,000m3 of the required material was placed on the frontage. 

 

The second stage was undertaken the following October when approximately 20,000m3  of material was placed on the frontage by the same method.

 

Chichester Harbour is a thriving recreational boating harbour and maintenance of the approach channel is therefore essential for the safe passage of vessels in and out of the harbour. Working collaboratively with the Harbour Conservancy, the nourishment material was sourced from the navigational maintenance dredge of this approach channel. This ensures that material is not lost from the sediment system: The 'beneficial use of arisings'.

 

 

Beach Nourishment 2002

 

The 2002 project was carried out as part of the Council's Beach Management Strategy Plan for the southern frontage of the Eastoke peninsula. 

 

Officers at Havant Borough Council secured grant aid of £100,000 from the Department for Environment, Food & Rural Affairs (DEFRA) who funded the works.

 

The Council appointed Westminster Dredging Ltd to undertake the works which were carried out in May and June 2002 using the dredging vessels "Sospan" and "Sospan Dau" using the same "rainbowing" method.

The works were undertaken at this time of year so that the material would be sorted by wave and tide throughout the summer period in order to develop a natural resilience to the winter storms.

The material was sourced from the navigational maintenance dredge of the approach channel to Chichester Harbour.

                                           

Extensive post project monitoring of both Hayling Island and the Witterings was carried out to ensure that any effects of the operation were identified and that suitable mitigation measures were implemented.
 
The beach nourishment works restored the beach levels and improved the standard of protection against storm events.
 
 

1997 Navigational Dredge and Beach Recharge

 

The 1997 project was undertaken in partnership with the Chichester Harbour Conservancy, involving the removal of over 25,000 cubic meters of shingle from the entrance to Chichester Harbour. The arisings were then deposited onto the southern shoreline of the Eastoke peninsula, which successfully extended the life of the beach and improved the standard of protection.