APPENDIX 2

 

Extract from Local Development Scheme setting out the timetable for the production of documents. (NB: The Local Development Scheme is reviewed annually but will be updated on the council’s website – www.havant.gov.uk/havant-4314).

 

Local Development Document - Core Strategy Development Plan Document

 

 

 
Pre Production and Technical Work
 
October 2005 – May 2006
 
Issues and Options: Informal Consultation
 
July – August 2006
 
Consultation on Preferred Options
 
March – April 2007
 
Date for Submission to SoS – Including Public Consultation
 
November 2007
 
Pre-Examination Meeting
 
March 2008
 
Examination
 
June – July 2008
 
Adoption
 
February 2009

 

 

Local Development Document - Allocations Development Plan Document

 

 
Pre Production and Technical Work
 
November 2006 – May 2007
 
Issues and Options: Informal Consultation
 
June – July 2007
 
Consultation on Preferred Options
 
March – April 2008
 
Date for Submission to SoS (Inc Public consultation)
 
March 2009
 
Omission site consultation (Reg 32)
 
June – July 2009
 
Pre-Examination Meeting
 
August 2009
 
Examination
 
November – December 2009
 
Adoption
 
September 2010

 

 

Local Development Document – Statement of Community Involvement

 

 
Pre Production and Technical Work
 
November 2004 – January 2005
 
Issues and Options: Informal Consultation
 
March – April 2005
 
Consultation on Preferred Options
 
July-September 2005
 
Date for Submission to SoS – Including Public Consultation
 
January 2006
 
Pre-Examination Meeting
 
April 2006
 
Examination
 
June 2006
 
Adoption
 
October 2006