Such a large amount of material being injected into the sediment transport system, resulted in the rapid transport of material along the frontage. In 1987 timber groynes were built in order to try and control the transport rate along the replenished area and in 1990 a rock groyne was constructed to further reduce loss of material around Eastoke Point.
Beach nourishment is the placing of material from offshore onto the beach, in order to maintain the required standard of protection along the frontage for the residents of Eastoke, Hayling Island.
In 1985 the beach nourishment scheme was implemented, creating a man made beach in front of the now redundant sea wall. Coastal processes are constantly eroding this frontage and without intervention the redundant concrete seawall would again be exposed. The result of this would be a return to regular serious flooding of Eastoke, through continuing erosion of the coastline.
The wave energy dissipation diagram shows how the beach profile created through nourishment will absorb the wave energy and help to prevent overtopping.
The shingle beach along the southern frontage of the Eastoke peninsula is the first line of defence against the threat of coastal erosion and flooding. The Council is the Coast Protection Authority that enables the use of permissive powers to manage these risks when it is considered in the Public interest. The Council developed and approved a Beach Management Strategy Plan that identified the most effective approach to managing this frontage; this decision was made after considering all economic, environmental and technical criteria. The beach nourishment works are one element of this preferred approach to managing this frontage and will restore beach material that is moved out of the area by natural coastal processes.
Council Officers have been monitoring the coastal processes around the Eastoke area over many years and have determined that wave and tidal action moves shingle in both directions along the beach from a drift divide around the middle of the frontage. Part of this material therefore moves eastwards along the frontage and into the entrance to Chichester Harbour. This material is then moved by strong ebb tidal currents at the entrance to the Harbour and comes to rest approximately a kilometre offshore.
(To view the images click on the thumbnails above. To return to this page use your browser's "Back" button or equivalent. )
In September 2008, Havant Borough Council successfully completed phase one of the Beach Nourishment scheme placing 25,000m³ of material on the frontage of Eastoke. After securing funding from the Environment Agency, Havant Borough Council now intends to carry out the second phase of the operation this summer. This involves placing a further 65,000m³ of material on the frontage to raise the beach to the recommended 1 in 200 year Standard of Protection. The works took approximately 1.5 months to complete.
Work started on the 19th June 2009 and was completed on 2nd Aug 2009.
For further information on the 2009 Beach Nourishment scheme please follow the link below:
Following the successful completion of the study as described above Havant Borough Council applied to the Environment Agency for funding to take the scheme forward.
This proposal was adopted after HR Wallingford was commissioned to develop the Eastoke Point Coastal Defence Study 2009 on behalf of Havant Borough Council. If work is not undertaken up to 1,700 properties on the south east of Hayling could be at risk of flooding over the next 100 years.
The Environment Agency gave technical approval on the 5th August 2010 to commence detailed design of the scheme and to obtain the necessary planning and other consents to enable the main scheme to be constructed. The construction of the main scheme however is dependant on there being sufficient funds from central government available.
The development stage commenced in September 2010 and it is hoped that the design will be completed and the necessary consents obtained by early 2012 dependant on the amount of funds made available by the Environment Agency.
The new project includes:
Preliminary site works were carried out in Winter 2010 to determine the current condition and positions of the defences, works on the detailed design started in the New Year. Once our Coastal Engineer develops the key specifications for the scheme to ensure it provides adequate coastal protection, we will be holding further public exhibitions to determine your views on the designs. Follow the link below for current updates of the project.
For any questions or more information please contact Clive Evans on 02392 446 617 or clive.evans@havant.gov.uk
Click here to see Current Updates of the Eastoke Point Coastal Defences Works>>