Emsworth Strategic Project

The aim of the liveability project for Emsworth is to make improvements to crossing the A259 and reducing the effects that the road has on the community.

 
Latest News Progress
Octber 2006
  • Roundabout, subway, railings and ramp completed. See photographs below
July 2006
  • See below for progress on various elements of the Emsworth Liveability Projects' progress
 

Roundabout A259

 

Emsworth Roundabout All works completed
Before Liveability works Emsworth roundabout After Liveability works Emsworth roundabout
Before After

 

Subway

Artwork has been installed in the subway

Emsworth subway Emsworth subway
Emsworth subway Emsworth subway

 

 

Subway art work Emsworth

Subway art work Emsworth
Original artwork for the subway
 
 
Emsworth Ramp Steps on path replaced with an anti slip ramp to facilitate disabled access and three new lighting columns installed.
Subway steps before-Emsworth Subway steps after-Emsworth
Before After

 

Brickwork repairs complete*
Mirrors installed*
All brickwork has been cleaned*
*The above three items have been funded by HCC
New handrails in place
New drainage channels installed

 

Railings

New railings have been erected around the subway and decorative plaques have been fixed to the railings.

Emsworth Plaques Emsworth Plaques

 

Footpath to Brook Meadow

Brook Meadow Bridge before Anti-slip on bridge Brook Meadow
Before After
Initial section of path completed and wire netting has been removed
Anti-slip on bridge and treatment of woodwork complete
 
 

Improvements to crossing North Street

Improvement of island in North Street before Improvement of island in North Street after
Before After
The crossing was widened to provide a safe refuge in the centre of the road, with additional tactile paving to aid partially sighted pedestrians. Drop kerbs were re-aligned to provide a straight crossing point.
 

Vehicle & pedestrian signage and lighting

  • New pedestrian finger signs and vehicle signing to car parks will be installed early in the new year.
  • New decorative lighting on the A259 will be installed, commencing in December 2006.
 
 

Budget

Current spend Actual/Commitments £190, 000, with the small amount of additional work left, anticipated that the final spend will be close to the allocated £200,000.
 

History

 
The main features of the Liveability Project in Emsworth were identified as:
  • Improvements to the North Street Subway
  • Link from the subway to the car park
  • Improvements to crossing North Street
  • Improvements on the A259
  • Link to Brook Meadow
  • Treatment of the wooden bridge/walkway
Emsworth map