Skip Navigation

Waterlooville Recreation Ground

 

Latest

News

Project progress

Summer 2008

New play equipment in Jubilee Park

  •  Climbing wall and climbing rocks, i (intelligent) play interactive electronic sound unit  and Altima climbing poles installed. All are being well-used by a wide range of the community from the morning joggers, dog walkers, mums and toddlers and teens!
  •  The Gravity bike track is coming soon! Watch this space!

New equipment at Jubilee Park

October 2007
  • The Contractors have experienced a small delay on other projects and are now due to start on site on October 22nd.
September 2007
  • Contractors have been appointed and works are due to commence on or around 30 September (weather permitting). 
  • The Liveability funding is sufficient to start phase 1 of the nature area works, drainage of the whole park and installation of the MUGA. The drainage part of the works is a complex contract and involves the movement of large machinery in the park and delivery of large quantities of material by bulk in eight wheeled lorries. 
  • There will be disruption to the park.  In particular the drainage contractor requires the use of two thirds of the Milton Road car park for the duration of the contract (estimated at approximately 10 weeks - the weather will be a key factor which is likely to affect these estimates).  A temporary compound will be fenced off in this area thus severely restricting the available car parking space.  A pedestrian access will be maintained to the scout hut/toddler group hut.
  • The plans are available to view here  <<Waterlooville Rec Drainage Plan 677 Kb >>
    <<Waterloville Rec Woodland Masterplan PDF 627Kb>>
October 2006
  • High pressure cleaning and survey of existing underground grainage system completed
  • Four options produced by consultants for the Nature Areas whilst drainage consultants, Turftrax, have produced options for drainage systems.
  • MUGA awaiting planning consent
  • Following break in weather and ground conditions unfavourable for heavy plant and machininery works. Programme is therefore to delay drainage until August 2007 to commence immediately after the end of the cricket season.
  • Works on old allotment site likely to start April/May 2007.

July 2006

Waterlooville Recreation ground temporary nature area

  • A temporary nature area has been established on the old allotment site. Specialist advice has been sought to determine a future wetlands position for the site. The drainage scheme is due to start on site in July 2006. Once the drainage is in place the new pathway and the multiuse games area will start.In the meantime the contracts are being tendered and planning permission is being put forward for the Multi Use Games Area ( MUGA ). 
 
 
 

Background to the project

The Council engaged with the stakeholders of the park, adjacent residents and nearby schools to find out how you would like this money spent in the park at a workshop on 1st June 2005. Ideas from the workshop were costed and a further wider consultation was held asking local residents and park users to prioritise those costed ideas. This prioritisation exercise was analysed and the results are shown below with the schemes in priority order.
The budget for the recreation ground is £319,000. A gap is drawn under £320,000 where there is funding from the current budget. Should a project above the grey line be unable to be met or there be budget remaining then the next project on the list will be picked to go ahead. The Council will work towards securing additional funding in the future so that some more of the projects can be realised. It is intended to start work on the selected projects as soon as possible.
 
Scheme
Votes
Budget
Cumulative Budget
Nature Garden
164.5
20,000
20,000
New Paths
106.55
75,000
95,000
Drainage scheme
96.05
125,000
220,000
Multi-use Games Area
94.75
80,000
300,000
Allotment reinstatement to parkland (completed)
78.75
20,000
320,000
       
Spinning / Rotating Activity hub
66.5
85,000
405,000
Climbing Boulders Activity Hub
63
65,000
470,000
* Lighting
54
?
 
Fit Trail
39
27,000
 
Water Activity hub
36.5
55,000
 
Renew existing paths
36.25
110,000
 
Sand play activity hub
33.5
40,000
 
Milton Road entrance
33.05
15,000
 
Rowlands Avenue entrance
14.05
15,000
 
 
* Note: Lighting was not presented as a specific scheme but a large number of people put this forward on their forms under ‘other’ and the consultation workshop also supported the idea that pathways and the MUGA will be lit. It is intended that the new paths above and the Multi-use games area will include some form of lighting for users of the park in the winter. It is also included in the above list as a separate scheme as it scored under other in its own right and should money become available additional lighting will be considered as appropriate.
 
Waterlooville Recreation Ground consultation and examples of children's perceptions of 'good' and 'bad' parks
 

Click here for information about the allotment reinstatement and clearing wildlife.

See how the site was cleared and the wildlife discovered.
 
 
 
 
 
 
 
| Borough of Havant - Home | What's New | Site Map | Search | Help | Complaints | Terms and Conditions | Feedback | Web Accessibility | Skip Nav |