Local Development Scheme (
LDS
)
A Local Development Scheme (LDS) is a
timetable that indicates the key milestones for individual Local
Development Documents (
LDDs
) with an indication of
what and when will be undertaken.
The council’s last LDS was approved by the Government Office for the
South East in October 2009 and was published here on the website
and as a paper document. However, the
LDS
no longer needs government
approval. In view of this, and that the programmes for individual
LDDs
are
subject to frequent change, the council has decided that updates of
the
LDS
will now only
be published as an ‘active’ page on this part of the website.
The following
LDDs
have been adopted:
Other approved Supplementary Guidance
includes: Waterlooville Town Centre
Urban Design Framework and Provision and
Improvement of Playing Space for New Housing Development
As of August 2011, the timetables for LDDs
currently in preparation are:
Development Delivery
(Allocations) DPD
|
Pre-production work including Options
consultation and Sustainability Appraisal
|
Ongoing
|
|
Regulation 25 consultation (including
sustainability re-appraisal &
consultation)
|
Autumn 2012
|
|
Pre-submission publication and
consultation
|
Spring 2013
|
|
Submission to Secretary of State
|
Autumn 2013
|
|
Pre-Examination Meeting
|
Winter 2013
|
|
Examination (Start)
|
March 2014
|
|
Inspector’s draft report
|
April 2014
|
|
Inspector's final report
|
May 2014
|
|
Adoption and publication of document and
revised proposals map
|
June 2014
|
Statement of Community
Involvement (First Revision)
|
Pre-production work
|
July – September 2011
|
|
Pre-draft consultation on content
of SCI
|
September – October 2011
|
| Consultation on Draft Statement of Community Involvement (First
Revision) Document |
7 November -19 December 2011 |
|
Adoption and publication of document
|
Feb 2012
|
The Developer Contributions
SPD
is no longer being
taken through to adoption. In light of comments received and
recent developments regarding the Community Infrastructure Levy
(CIL), future resources will be directed towards developing a CIL
charging schedule. It is anticipated that much of the work
undertaken in developing the
SPD
will be transferrable
to
CIL
and will
help the council meet the timescales set out in the
Front Runner 2 Programme.
CIL
is not part of the
LDS
but further details can be found here, including
timescales>>