This page is currently being updated.. If you have any further queries please contact
webmaster@havant.gov.uk
Langstone Oyster Beds, Hayling Island
Restoration Project, 1996 - 97
The Langstone Oyster Beds were restored for nature conservation in
1996 / 97. The following describes the major civil engineering
project which achieved this successful restoration and led to the
site's designation as Havant Borough Council's first Local Nature
Reserve. For earlier history of the site, and its subsequent
use, see our
main
Oyster Beds page.
Towards a
Solution ...
Crisis Point
...
Environmental Impact
Assessment (EIA) ...
Site Access
...
Working
Area ...
Tenders and
Contract Award ...
Further Planning
Consent ...
Work on Site
...
The Problems - or
Challenges ...
Towards a Solution
From 1987 the Council explored various options for overcoming
the problems of the Oysterbeds including letting the site to
another commercial operation, passing over the ownership to the
County Council (who were considering its use for oyster breeding as
an adjunct to training provided at Sparsholt Agricultural College)
or removal and/or improvements to the extant embankments.
Unfortunately it quickly became clear that none of the proposed
uses would generate sufficient income to sustain the maintenance of
the embankments.
In 1990 the County Council assisted the Borough Council by
investigating possible solutions for improving the amenity and
safety of the site. They engaged consultants to advise on the
facing, redistribution, and protection of the disintegrating
embankment walls. At a time when the Council's finances were in
crisis due to problems collecting the new Community Charge,
solutions offered proved to be too expensive, with some options
costing in excess of £1M with no guarantee of sustainability.
In 1993 an application was made to the
EEC
for funding under the
"Life" Programme which if successful would have seen the site
reorganised, but ultimately was unsuccessful. No external
assistance was available for the Borough; equally it had no funding
available on the scale necessary to carry a conventional civil
engineering project forward.
Crisis Point
Public Opinion was divided. There were substantial groups in
support of maintaining the status quo with the public being given
access to walk on the deteriorating walls and believing that they
would remain as they were with little or no maintenance. Others
were as vocal in pointing out the readily apparent hazards and
risks, particularly to children. Having carried out various studies
and investigations it was clear by 1994 that the stage had been
reached where the Councils options were limited but a choice had to
be made. It was unable to maintain the site in a safe condition. It
could not afford to arrange the removal of the unsuitable
materials. The longer it delayed in removing the unsuitable
materials the higher the costs would become as material was spread
over the harbour floor. Similarly the deterioration of the walls
and the spreading of the unsuitable material over the harbour
mudlands made it more likely that the Council would be attacked for
failing to fulfill its duties under the Habitats Directive.
As maintaining the walls was too expensive and taking no
action exposed the Council to the risk of high costs either as the
result of accidental injury to the public, or if it was required to
remove material from the harbour, it was decided to initiate a
Planning Application proposing the removal of the unsuitable
material and the restoration of the site to, as far as was
possible, the condition pertaining in the 1970s before the tipping
took place.
Environmental Impact Assessment (EIA)
Due to the international designations in force at the site an
EIA
was
required as input to the Planning process. Borough Councillors,
mindful of the need for an environmentally acceptable solution,
required that the
EIA
should investigate all
possible alternatives, not simply the alternative proposed by the
officers of the Council.
Emergency finance was found to allow Adams Hendry, Chartered
Town Planners and Environmental Consultants of Winchester to be
engaged in 1994 to undertake the
EIA
, which was completed
in January 1995. Their final report advised that the prospect of
the Council being required to remove the alien material from the
harbour was increasingly likely as environmental legislation was
strengthened and so supported the materials removal.
The publication of the
EIA
was used by the
Council as an opportunity to hold both a Member's seminar and a
public meeting in February 1995. These meetings revealed that
opinion was equally divided between three desired outcomes: to
leave matters as they were; to remove the material as planned; or
to have another attempt at restarting the oyster fishery as a
commercial concern. Whatever course of action was taken, it
appeared that two thirds of the local residents would be
opposed.
Site Access
The
EIA
found
that even getting to the site would be problematic. After the
material had been originally tipped in the 1980's, subsequent
development had closed the haul road used at that time. Three land
routes were considered in the
EIA
, all having to cross
the Hayling Billy Coastal Path. A northern route was ruled out due
to the ecological value of the grazing marsh it would cross.
Two southern routes, with access taken from a track locally
known as "Station Road", were also identified, one direct but lying
upon reclaimed land, the other less direct but partly using the
route of the Coastal Path. Since there would be considerable
technical difficulties in constructing a haul road capable of
carrying heavy lorries over ground that was partially comprised of
tipped domestic refuse, the Council adopted the route involving the
construction of a temporary diversion of the bridle-way and
footpath across the open land to the west of the existing bank that
bounded the Hayling Billy Coastal Path.
This could be of a relatively light construction as it would
only have to carry pedestrian loads and would enable the old
railway embankment, which was known to be sound, to be used to
carry the heavier lorries. Fencing would be provided to guide users
onto the diverted Coastal Path with signs advising the public of
the diversions and the reasons for the works. Risk Assessments were
carried out to determine the best layout for the fencing and
signs.
The only road crossing to the island, the single carriageway
A3023 [Havant Road], was rated as traffic sensitive during peak
hours during the winter period and all day during the summer. Lorry
movements into and out of the site during peak periods would be
limited to working from 1 October to 30 April each year, with
positive traffic control when more than 30 vehicles an hour were
using the access.
At the seaward end of "Station Road" the Hayling Billy Coastal
Path ran through a car park. There were already conflicts between
turning cars, cyclists, equestrians and pedestrians, and adding
lorries using the haul route to this meant there was no alternative
but to close the car park, although an alternative car park to the
north of "Station Road" could be used.
Working Area
It was envisaged that rubble removed from the embankments would be
taken to a portable crusher elsewhere on the site, crushed, and
stockpiled until removal. For the purposes of the planning
application the crusher was specified as being portable plant of a
size capable of being moved on the highway without special
arrangements. The noise levels of the crushing plant and other
plant would mean that such plant could only be operated between the
hours of 7 a.m. and 6.30 p.m. on
weekdays.
The crushing area would be surrounded by a temporary bank of
material two metres above surrounding ground level in order to
reduce the effects of noise from the crushing plant. The
stockpiling of crushed material would be contained within this bank
to act as additional noise protection. The crushing plant would
then be situated partially below ground level on a platform
temporarily reclaimed from one of the lagoons. Material for banks
and reclamation would use some of the first material removed from
the embankments.
The
EIA
considered habitat loss and to compensate for this some of the
unrecyclable material removed from the embankments (expected to be
approximately 10% of the total volume) would be placed on a small
section of the former outer embankment to form a roosting island.
It was noted that it would be some years before it was sufficiently
stable to be fully suitable for this purpose, and in the interim
the value of the site to wildlife was likely to be
compromised.
In order to allow maximum flexibility for a successful
contractor to identify a market for the crushed material a works
duration of three winter periods (1 October to 30 April) was to be
allowed.
Tenders and Contract Award
On the basis of the consultations and the content of the
EIA
, Planning
Consent for the outline proposals to completely remove the alien
material was obtained in September 1995. The Consent carried a
large number of Conditions covering enabling and temporary works,
programming, environmental measures relating to noise, mud and
dust, aftercare and management as have been described.
For the first time the Council's engineers now had a clear
idea of exactly what would have to be incorporated into any scheme
to resolve the problems at the Oysterbeds. It was now necessary to
find the cost of the project to allow future budgetary provision,
and it was decided on that basis to invite Tenders.
Havant has a history of carrying out works under its own
Specifications and Conditions of Contract and was quite a late
convert to the I
CE
Standard Conditions.
With regard to the Oysterbeds it was considered that none of the
standard Forms of Contract would meet the requirements of what was
being attempted, and so documentation was drafted envisaging the
award of a "quarry rights partnership" to the successful
contractor. The Planning Conditions became the Conditions of
Contract, these clearly setting down the hours of working and the
many and various restrictions, with the expected end result of the
project forming in effect a Performance Specification.
In recognition of the delicate environmental attributes of the
site, non-contractual partners were invited to provide expert
advice to the contractual team of Council and contractor. The
project was intended to be carried out in such a way that
environmental objections (in particular) could be quickly laid to
rest. To this end, the project team was to be extended to include
representatives from the following organisations:
- Hampshire County Council - adjacent landowners who also had a
very active Countryside team managing the Coastal Path and Nature
Reserves elsewhere on Hayling;
- English Nature - as the Governments statutory advisors on
nature conservation officers of the Hampshire and Isle of Wight
Team had been involved in evolving advice regarding the most
suitable methods for carrying out the work;
- Royal Society for the Protection of Birds - adjacent owners of
a large Nature Reserve in Langstone Harbour, and with expert
knowledge of how birds would react to the project and how the
project could encourage wildlife afteruse;
- Hampshire Wildlife Trust - managers of the Farlington Marshes
Nature Reserve on the opposite shore of the harbour, again with
intimate knowledge of the ecosystems and how the project would
impact on them.
Invitations for expressions of interest were placed in the
industry press at the end of 1995, and from the responses received
a Select List of Contractors was produced taking due consideration
of experience in the type of project. Preliminary meetings were
held with a shortlist of four interested tenderers early in 1996
with Tender Documentation being issued to those four companies at
the beginning of March, for return on 1 April 1996.
Whilst two of the group declined to submit tenders when they
had seen the documentation, the others submitted tenders by the
return date. Of the two, H. T. Hughes and Sons (Transport) Ltd of
Fareham in Hampshire (hereafter referred to as "Hughes", now part
of the Sita Group) submitted a bid whereby the works would be
carried out at no cost whatsoever to the Borough Council. After
evaluation of the returned tenders, and a period of some surprise
that a solution appeared achievable, a proposal was taken through
the Council's various Committees to proceed with the project rather
than wait for finance to become available (this now not being
necessary) and this company was duly engaged as contractor to the
Borough Council during the summer of 1996.
Further Planning Consent
Some 60% of the Planning Conditions contained within the September
1995 Consent required "further information" before the contractor
was able to start on site. This was not only intended to allow a
successful contractor maximum flexibility in carrying out the work
in a manner suitable for his own resources, but also to allow the
partnership to become established "in action". In order to satisfy
the Conditions, Hughes and the Council's engineers promoted a
second Planning Application, covering the methodology by which
Hughes intended to carry out the works.
Working through the summer, representatives of the Council and
Hughes worked closely with the non-contractual partners and
advisers and produced a comprehensive second Planning Application
which was duly approved in September 1996, with further minor
Conditions, allowing a start from 1 October.
Work on Site
In light of the significant environmental value of the site the
Council was concerned that there was a very real possibility of
action by environmental campaigners, this being around the time of
Newbury. The site could hardly be more protected by environmental
legislation, and some residents had been vocal in their opposition.
Two critical decisions were therefore made before starting on site.
The first, already described, was that the management of the
project required input not only from the contractual parties but
also those parties expert in matters relating to the conservation
designations, thereby hopefully removing any objections on that
front. The other was that the media should be fully informed of the
engineering and environmental details and benefits of the project.
To this end regular Press Releases were released throughout the
summer informing the public of the schemes progress through the
planning stage and considerable interest was shown by both local
newspapers and radio stations.
When the news advising of the start on site was published,
opposition was indeed mustered and for a time it did appear as
though the Council was about to be faced with a "Newbury" style
occupation. Fortunately nothing became of this threat and Hughes
duly took access to the site on 16 October. Within two weeks the
temporary works were in place, North Hayling Halt car park closed
and material started to be removed from the embankments at the
north of the site.
The Problems - or Challenges
It was at this point that the effect of the restrictions imposed
upon the site (
SSSI
status etc.)
became apparent. No preliminary ground investigation had been
carried out since to even take the simplest mechanical plant onto
the site would have required the installation of all the temporary
works, diversions and closures. All parties had made assumptions
(in good faith) but the material now being removed from the first
embankment at the northern extremity of the site was significantly
different in composition from that expected from the hearsay
records of the time.
Instead of an embankment of "pure" rubble tipped cleanly onto
the Victorian shingle remains, what was actually on site was a
combination of two effects. Firstly, the rubble originally must
have had a high proportion of soil within it, which in places had
formed into an inner soil core within the embankment. Secondly, the
underlying shingle had deformed over the years of burial and had
migrated up into the body of the embankment. The result was that
the original intention of cleanly removing all the tipped material
and leaving the underlying Victorian shingle banks scraped clean,
could not be achieved.
Of immediate concern was that material with which to reclaim
the temporary working platform upon which to place the crusher was
unsuitable for that purpose. A rapid reassessment of layout of this
part of the site by the Project Team led to a decision to rotate
the crusher's orientation through 90 degrees so that instead of
being wholly on the platform it could now be placed on what was the
original shoreline embankment. This was composed of chalk over 60
years old and was firm enough to allow a shelf to be excavated from
it to achieve the required lower elevation of the crusher as
required by the Planning Conditions. The reclaimed platform would
now be used solely for stockpiling crushed material ready for
removal from the site.
Less immediate but potentially more serious was the effect on
the economics of the project for the contractor. It was more
difficult to him to remove material from the embankments, and of
course a lower proportion than expected was of recyclable quality
which would lower the overall income from the project. The
originally expected 10% unrecyclable portion was now expected to
reach 50%, or 50,000 tonnes.
Since the contractor now had complete access to the site it
was agreed to carry out a programme of trial holes within the
various embankments. This led to the surprising discovery that
although from the outside all the embankments looked the same,
under some a substantial core of rock chalk was intact, whilst
within the sheltered northern lagoons embankments were composed
almost exclusively of clay soils of varying quality.
The Project Team quickly realised that the chalk embankments
could be left in situ once the surface covering of rubble had been
cleared, and likewise the clay since its erosion would cause no
damage to the harbour environment, and might in fact provide useful
material to feed the surrounding mudflats.
In theory therefore a solution to the challenge which had
arisen had been found. Although the expected income from the
project had reduced, so too had the amount of work. The contractor
volunteered to continue on a basis of no net cost to either party,
and it is to his credit that he did not walk away from the site but
worked hard with all the parties to secure a successful outcome.
This attitude was no doubt partly due to the high level of public
interest in the project but reflected a commendable commitment both
to the contract and to the environment.
However matters are never so simple as they first appear.
Incorporating the changes suggested above would be a significant
departure from the scheme for which Planning Permission had been
given (twice) and it was not just a Council decision - being within
the
SSSI
the full list of consultees would have to give their
approval.
It was now that the management arrangements for the project
paid dividends. The involvement of English Nature, the
RSPB
, and the
Hampshire Wildlife Trust on the project management team meant the
resolution of the problem was developed in the presence and with
the input of the major parties to the planning consultation
process. In fact this presented an opportunity whereby those
non-contractual partners could meet some of their aspirations for
the site which perhaps the original proposals would have not met.
Therefore the revised arrangements for clearing the site (which
were still driven primarily by safety concerns) could now, by
"taking advantage of the contractors presence", include significant
improvements to the habitats at the site.
As an example, the original plans would have seen all the
embankments removed and the unrecyclable material used to recreate
within one of the by then tidal lagoons, a roosting island. It
would have been perhaps two or three years before vegetation had
colonised the island for it to be of significant benefit to
wildlife. In the new arrangements some existing embankments would
be severed at their landward end with minimum disturbance to the
vegetation and so would remain available uninterrupted.
Planning Permission was obtained for the third time for the
changes, and works now progressed in the main according to plan.
The reduced amount of material to be removed, and the eagerness of
the contractor to reduce the time plant was on site, meant that the
project was substantially completed on 23 May 1997, only seven
months after starting; in itself a major local media event with
coverage by the local newspaper and
BBC
and Independent Local
Radio.
The final quality of surface finish to the embankments was
very good considering the circumstances. Although the underlying
Victorian embankments were only exposed in a very limited number of
places, the Council had successfully achieved its objective of
removing the dangers from the site, leaving in their place
embankments which would be formed into sustainable profiles by the
action of wind and wave.
The embankments have now been exposed to some severe weather
events over the past few years including an exceptional event on
10th February 1997 which completed a civil engineering
task scheduled to last three weeks, in 1½ hours. This profiling by
natural forces has resulted in a textbook storm beach forming on
the outer [harbour] edge of the embankments, with finer material
overtopping and covering the more blocky material beneath. This new
profile has provided excellent roosting facilities for wildlife
which it was feared would be displaced from the site, with the
result that overall seabird numbers are up 20% on the numbers
prevailing before the work started.